A small stretch of the #PinkLine is set to become operational (for public) from 14th November, while the wait continues for the Underground section to be completed.
Next up: when will the #BlueLine join the club and complete the Olympics metro picture? #Bangalore
Next up: when will the #BlueLine join the club and complete the Olympics metro picture? #Bangalore
The Olympics are held every four years.
Namma Metro, however, takes twice that time to bring a new line into operation.
With the #YellowLine finally opening after eight years of construction, we’ve entered what could be called the “Namma Metro Olympic cycle”
•Pink and Blue ders in key positions—both in the government and at BMRCL—must start showing genuine seriousness, especially after witnessing the prolonged delays across all metro lines. Without consistent monitoring, nothing will improve, and the public will continue to bear the brunt. @TheMetroRailGuy
5
6
138
5,360
6 Elevated Stations on #PinkLine
• Kalena Agrahara
• Hulimavu
• Bilekahalli–IIMB
• NS Palya – J.P. Nagar 4th Phase
• Jayadeva Hospital
• S.G. Palya (Suddagunte Palya)
• Kalena Agrahara
• Hulimavu
• Bilekahalli–IIMB
• NS Palya – J.P. Nagar 4th Phase
• Jayadeva Hospital
• S.G. Palya (Suddagunte Palya)
Bro can u provide the name of all metro stations
2
0
57
3,842
Aerial View of #PinkLine Metro Stations!
All set for the inauguration on Nov 13th and open for passenger operations starting the next day.
#NammaMetro #Bangalore
All set for the inauguration on Nov 13th and open for passenger operations starting the next day.
#NammaMetro #Bangalore
3
12
219
7,085
With the #PinkLine opening to commuters on Nov 14th, Namma Metro crosses 100 km. Fifteen years after launching in 2011, we should honestly be at double that distance by now.
Still, a milestone is a milestone. Time to celebrate and welcome the new line. @TheMetroRailGuy
Still, a milestone is a milestone. Time to celebrate and welcome the new line. @TheMetroRailGuy
🎊 🎉 🥳 At last, the day has arrived!
•A historic milestone for #NammaMetro, as the network expands to 94.35 km with the inauguration of a new 19.2 km #YellowLine today.
•With both the Blue and Pink Lines under construction, the metro network is poised for significant s of the city. @TheMetroRailGuy #Bangalore
10
33
429
14,798
#PinkLine
Opening a new line is good news and it’s great to see a few km added to our metro network 🎉🥳.
But 9 years for a 7.5 km stretch? That’s 0.83 km a year - SHAME and shows the level of inefficiency. No one will take the blame, but everyone will rush to take the credit
Opening a new line is good news and it’s great to see a few km added to our metro network 🎉🥳.
But 9 years for a 7.5 km stretch? That’s 0.83 km a year - SHAME and shows the level of inefficiency. No one will take the blame, but everyone will rush to take the credit
40
170
1,540
49,592
My very first post about the #PinkLine was back in May 2020 during the COVID lockdown.
Now, almost 9 years after Simplex first started ground work, we’re finally seeing the 7.5 km elevated stretch go operational in 2 days!
Total length of Pink Line is 21.38 km. #Bangalore
Now, almost 9 years after Simplex first started ground work, we’re finally seeing the 7.5 km elevated stretch go operational in 2 days!
Total length of Pink Line is 21.38 km. #Bangalore
#NammaMetro Pink Line 4 - Gottigere to Nagawara (21.38KM). Start point at Kalena Agrahara was a bit of surprise (see pics). And there were many surprises till Dairy Circle. #Simplex —> quite COMPLEX @TheMetroRailGuy @NaveenMIRROR @ChristinMP_TOI @bengalurutrains @KARailway
8
8
207
15,665
#BlueLine trial run from Baiyappanahalli -> KR Puram -> Doddanekundi
4
27
570
15,187
I am back Brother! And when you find time, spare some time to read this message as well 😉
Hope you are doing well!
Hope you are doing well!
pity @WF_Watcher isn't active on twitter anymore. they were at the forefront of pestering officials to open the Krishnarajapura <> Baiyappanahalli stretch after the CMRS "yes" came in September 2023.
I would know, i was right next in line. wake up > yell at people on twt to open that stretch > sleep :P
10
10
204
21,767
Hi Bala, thanks for asking! All good here, just been busy with new work and took a 3-month break from Twitter.
But I'm back now!
But I'm back now!
@WF_Watcher Hope everything is going well. Haven't seen any post from you for more than a month now
3
0
39
3,773
#YellowLine extension update.
#BengaluruMetro plans 9 stations to extend #YellowLine by 10.5km after Bommasandra; DPR soon.
Narayana Institute of Cardiac Sciences
Chandapura Circle
Old Chandapura
Thirumagondanahalli
Balagaranahalli
Attibele Ind Area
Yadavanahalli
Attibele
Attibele Terminal
@WF_Watcher
4
5
69
19,323
Bangalore Metro Updates retweeted
🚨 MC Interview: Bengaluru loves Metro but hates BMRCL? MD says realistic deadlines can change perception as 80% of problems can now be anticipated
@moneycontrolcom @OfficialBMRCL
moneycontrol.com/news/india/ben…
@moneycontrolcom @OfficialBMRCL
moneycontrol.com/news/india/ben…
19
21
122
8,878
#PinkLine update
#PinkLine update:
#BengaluruMetro files compliance on CMRS rolling stock observations; awaits Railway Board sanction & ISA certificate.
CMRS statutory inspection likely in 1st/2nd week of Sept.
Commercial ops from Sept-end, subject to govt nods.
@WF_Watcher
2
4
79
14,166
@krishnabgowda is inspecting #BengaluruMetro's #PinkLine underground line from MG Road to Shivajinagar today.
The 13.5km line links Tavarekere to Nagavara via MG Road. It'll open in Mar '27.
The 7.5km elevated line (Kalena Agrahara-Tavarekere) opens in Sept-end.
@WF_Watcher
1
1
23
9,312
A month-long smartphone deTOXIfiCation, and I’m back on Twitter today. Back to work now after 3 hours of torture in movie theatre!!
🙏🏃🤕🤕🤕
🙏🏃🤕🤕🤕
4
0
51
6,328
Shame: Another vital infra project neglected!
MVR Infra was awarded the #Whitefield Metro Extension contract in March 2024 with an 18-month deadline. It’s now been 28 months, not an inch moved ahead.
This 588-metre extension to Belathur Colony will add a reversal crossover, rain operations and frequency. It’s disappointing that such a small but critical project has been left stalled for years. Commuters would already be benefiting from better service had it been completed on time.
MVR Infra was awarded the #Whitefield Metro Extension contract in March 2024 with an 18-month deadline. It’s now been 28 months, not an inch moved ahead.
This 588-metre extension to Belathur Colony will add a reversal crossover, rain operations and frequency. It’s disappointing that such a small but critical project has been left stalled for years. Commuters would already be benefiting from better service had it been completed on time.
20
44
259
24,911
Pic 2: This is where the extension is supposed to be headed to
Pic 3: Barricades are thrown out upside down tells the whole story!
Pic 3: Barricades are thrown out upside down tells the whole story!
2
0
14
4,805
Posted this in October 2025
NEGLIGENCE- COMPLACENCY
MVR Infra was awarded the #Whitefield Metro Extension contract in March 2024 with a completion deadline of 18 months.
It’s been 19 months, and not even a centimetre of work has started. Hard to imagine when this will actually be completed.
This Belathur Colony is meant to enhance train operations through a reversal crossover-track facility. Neither the Government nor BMRCL seems interested in monitoring its progress. @TheMetroRailGuy #PurpleLine #Bangalore